| Month 1 | Design + Site Survey | Architect drawings (1,200-1,800 sf depending on lot), structural engineering, Title 24 energy calcs, MEP plans. Survey if no existing. | Plan set complete + ready for LADBS submittal. | Skipping pre-app meeting with LADBS planner — costs 1-2 correction cycles. |
| Month 2 | LADBS Permit Submittal | Plans submitted. Plan-check takes 30-60 days (state law caps at 60 for ADUs). Corrections typically 1-2 rounds. | LADBS permit issued. | Submitting incomplete plans hoping to 'fix in correction' — adds 4-8 weeks to gate. |
| Month 3 (Build Month 1) | Mobilization + Foundation | Site prep, utility locates (DigAlert), excavation, formwork, rebar, foundation pour. 28-day concrete cure begins. | Foundation inspection PASS. Anchor bolts verified. | Pouring before underground rough plumbing — costs $4-8K to re-cut slab. |
| Month 4 (Build Month 2) | Framing + Roof Dry-In | Floor system, exterior walls, interior partitions, roof framing, sheathing, weather wrap, windows installed. Roof shingles or membrane on. | Framing inspection PASS. Building dry-in confirmed. | Skipping water-tight roof before framing inspection — rain damage common in LA Nov-Mar. |
| Month 5 (Build Month 3) | MEP Rough-In + Insulation | Plumbing rough, electrical rough, HVAC ducting, gas line, low-voltage (data/cable/security). Insulation R-21 walls / R-30 ceilings. Energy audit pre-drywall. | MEP rough-in inspection PASS. Insulation inspection PASS. | Insulating before rough-in inspection — auto-fail at LADBS. |
| Month 6 (Build Month 4) | Drywall + Paint Prep | Drywall hung, taped, 3-coat mudded. Texture sprayed (typically light orange peel in LA). Prime + first finish coat. | Drywall inspection PASS. Walls flat under raking light. | Painting over uncured drywall mud — cracks visible within 6 months. |
| Month 7 (Build Month 5) | Flooring + Cabinets + Fixtures | Flooring (LVP / engineered hardwood / tile). Kitchen + bathroom cabinets installed. Countertop template + install. Tile work. Plumbing trim + electrical trim. | All trim inspections PASS. | Installing flooring before HVAC commissioning — duct dust + commissioning debris ruin finish. |
| Month 8 (Build Month 6) | Final Inspections + C/O | Final building inspection. Title 24 final compliance. Electrical final. Plumbing final. Gas pressure test. Certificate of Occupancy issued. | C/O in hand. Punch list 100% complete. | Closing the project before C/O — homeowner can't legally rent the ADU. |