| Month 1-2 | Schematic Design + Site Analysis | Architect schematic design, site survey, soils report, easement/setback verification, HOA review if applicable. | Schematic design approved by homeowner. | Skipping soils report — can require $30K+ foundation rework if expansive soil discovered later. |
| Month 3-4 | Design Development + Engineering | Construction drawings (CDs), structural engineering, MEP design, Title 24 calcs, CalGreen compliance, stormwater plan, landscape coordination. | CDs at 95%, ready for plan-check. | Submitting CDs at 75% — adds 2-3 correction cycles at LADBS. |
| Month 5-6 | LADBS Plan-Check | Plans submitted, 6-12 wk first-round review, corrections + resubmittals, permit issued. | LADBS permit number issued. | Not pre-meeting with LADBS planning + plan-check — costs 1-2 cycles. |
| Month 7 (Build Month 1) | Mobilization + Demo + Foundation | Existing structure demo (if applicable), grading per civil engineer, foundation excavation, formwork, rebar, foundation pour. 28-day cure. | Foundation inspection PASS. | Skipping geotechnical observation during foundation — voids structural warranty. |
| Month 8 (Build Month 2) | Framing First Story | Floor system, exterior walls, interior partitions, beam + post system, intermediate framing inspection. | Framing inspection PASS for first floor. | Pouring slab before pre-slab plumbing rough — costs $20K+ to re-saw. |
| Month 9 (Build Month 3) | Framing Second Story + Roof | Second floor system, second story walls, roof framing, sheathing, weather wrap, windows installed. Building dries in. | Framing inspection PASS for full structure. Building dried in. | Skipping water-tight roof before Nov-Mar — rain damage adds weeks. |
| Month 10-11 (Build Month 4-5) | MEP Rough-In + Insulation | Plumbing rough (whole house), electrical rough (200A service min, every circuit), HVAC (zoned if multi-story, ducting + condensers), low-voltage backbone, insulation R-21 walls / R-30+ ceilings. | MEP rough inspections PASS same-day. Insulation inspection PASS. | Insulating before rough inspection — auto-fail. |
| Month 12 (Build Month 6) | Exterior Lath + Stucco / Siding | Lath/scratch coat for stucco (3-coat system standard in LA), siding install, soffit, fascia, roof drainage. Exterior trim. | Lath inspection PASS. | Stuccoing before lath inspection clears — auto-fail. |
| Month 13-14 (Build Month 7-8) | Drywall + Finish Framing + Cabinet Install | Drywall hung + taped + 3-coat mudded, texture, prime, first paint, finish trim, doors, cabinets (kitchen + bath), tile. | Drywall inspection PASS. | Skipping detailed punch on drywall — surface defects telegraph through paint. |
| Month 15 (Build Month 9) | Plumbing/Electrical Trim + Paint Finish | Plumbing trim (faucets, toilets, fixtures), electrical trim (devices, fixtures, dimmers), 2nd-3rd paint coats, hardwood floor install + finish. | Trim inspections PASS. | Re-pulling power on trim — usually a circuit defect. |
| Month 16-17 (Build Month 10-11) | Final Inspections + Site Work + Landscape | Final LADBS, Title 24 final, Mech/Elec/Plumb finals, fire department final (if applicable), site work (driveway, patio, hardscape), landscape install. | All finals PASS. C/O ready. | Closing without final landscape inspection — some lots require it for C/O. |
| Month 18 (Build Month 12) | Certificate of Occupancy + Move-In | C/O issued, punch list 100%, warranty packet, move-in coordination, 30-day follow-up. | C/O issued. Warranty packet delivered. | Releasing final payment before C/O — homeowner can't move in legally. |