| Week 1 | Contract Signing + Initial Coordination | Contract signed. Initial deposit paid (typically 5-15%). Kickoff meeting with NPLD project manager + homeowner. Site walk-through confirms scope. | Contract executed. Kickoff meeting documented. | Skipping kickoff meeting — misalignment surfaces during build. |
| Week 1-2 | Design Finalization | If any design details were left open (cabinet door style, paint colors, fixture finishes), finalize now. Spec book locked. | Spec book signed. | Letting selections drift past Week 2 — long-lead orders blow up timeline. |
| Week 2-3 | LADBS Permit Submittal | Plans submitted to LADBS. Express permits clear same-day. Plan-check permits start 3-12 week review cycle. | LADBS project number issued. | Submitting incomplete — clock doesn't start, plan-check delays everything. |
| Week 2-3 | Long-Lead Material Orders | Cabinets ordered (4-14 wk lead time), appliances ordered (4-10 wk for premium), custom hardware, premium tile, specialty fixtures, structural steel. | All long-lead POs acknowledged with ship dates. | Waiting for permit approval before ordering — adds 6-10 weeks to back end. |
| Week 3-4 | Schedule Lock-In + Resource Commitment | Build start date locked. Subcontractor crews committed (in-house at NPLD). Equipment + tools scheduled. Dumpster + portable toilet scheduled. | Schedule shared with homeowner. Resources committed. | Floating schedule — "we'll start when we can" — creates accountability gaps. |
| Week 4 | Certificates of Insurance + Compliance | NPLD COI on file with homeowner. HOA COI if condo. Workers' comp + general liability certificates filed. | All COIs delivered + verified. | Starting without COI on file — homeowner uninsured against contractor incidents. |
| Week 5-8 | Permit Approval Window | LADBS review continues. Corrections addressed within 48 hours of receipt. Most projects clear in 1-2 cycles. | Permit issued + posted on jobsite. | Slow correction responses — adds 1-2 weeks per cycle. |
| Week 8-10 | Pre-Build Site Prep | Neighbor notifications (3-7 days before demo). Site protection plan finalized: dust containment, floor protection, landscape protection. Dumpster delivery confirmed. | Site protection ready. Neighbors notified. | Skipping neighbor notification — complaints + HOA fines. |
| Week 10-12 | Materials Delivery + Demo Day Ready | Long-lead materials arrive (or confirmed shipment). Demo day scheduled. Project manager + homeowner walk-through 24 hours before demo. | Demo day starts as scheduled. | Demo before materials are confirmed shipping — build idles during cabinet wait. |