| Week 1 | Site Survey + Engineering Scoping | Engineer walks ground-floor parking, measures clear height, identifies existing framing, photographs columns + headers, calculates seismic load. | Scoping report + ROM cost estimate. | Skipping the site walk — engineer designs blind, costs balloon at install. |
| Week 2-3 | Structural Engineering + Plans | Engineer designs moment frames (typically steel, occasionally heavy timber), foundation tie-downs, header reinforcement, lateral load path. Plans stamped + ready for LADBS. | Stamped engineering set complete. | Using a non-LA engineer — LADBS reviews 2x for unfamiliar engineers. |
| Week 3-4 | LADBS Permit Submittal | Plans submitted to LADBS soft-story division. Plan-check turnaround in 2026: 2-4 weeks for soft-story (priority-reviewed under Ordinance 183893). | Soft-story permit issued. | Submitting before tenant-notification requirements met — permit conditioned on tenant notice. |
| Week 5 (Build Wk 1) | Mobilization + Tenant Coordination | Project signage posted, tenant 7-day notices for parking impact, equipment staged, demo of existing finishes around moment frame locations. | All tenants notified per CA Civil Code 1954. | Skipping tenant notice — code violation, project halted. |
| Week 6-7 (Build Wk 2-3) | Foundation Tie-Downs + Moment Frame Footings | Foundation tie-downs drilled + epoxy-anchored, moment frame footings excavated + poured (28-day cure runs in parallel). | Foundation inspection PASS. Tie-downs inspection PASS. | Pouring footings before tie-down inspection — auto-fail at LADBS. |
| Week 8-10 (Build Wk 4-6) | Moment Frame Installation | Steel moment frames welded + bolted in place, header connections, lateral load path completed, secondary framing modified to accept frames. | Frame installation inspection PASS. Welds visually inspected + ultrasonic if engineered. | Skipping ultrasonic inspection on critical welds — engineer required, LADBS may require. |
| Week 11 (Build Wk 7) | Finish Restoration | Drywall, stucco, paint, flooring patches at frame locations. Parking lines repainted. Lighting verified. | Walk-through with property manager. Tenant access fully restored. | Closing without re-striping parking — tenants confused about assigned spaces. |
| Week 12 (Build Wk 8) | Final Inspection + Certification | LADBS final soft-story inspection. Engineer certification letter prepared. Recorded on building file. Owner's compliance certificate issued. | LADBS final PASS. Certification on file with city. | Closing without LADBS final + certification — compliance not on city record. |